Tuesday, March 31, 2009

progress of the bedrooms


Bedroom #1: first coat of paint is on. We're still trying to figure out what to do with the flooring. If bedroom #2 was any indication, unlevel floors are not to be taken lightly:


Bedroom two: victory! We're keeping our fingers crossed that the laminate settles the way it's supposed to.  There's a quarter-inch height difference between the two halves of the floor, mostly because the original floor throughout the entire space is a patchwork of different building materials, all in different stages of decay. There's one spot in bedroom two that balloons oddly and walking over it creates an Alice in Wonderland/funhouse mirror sort of effect of feeling like the ground is hurtling toward you. Unpleasant for now, but it looks like the flooring we put in a few days earlier has settled nicely.

No comments:

Post a Comment